" 13. Project Manager Paul is purchasing 100 laptops and 20desktop computers for her project, and the delivery of thecomputers is time-critical. Billie Jo would like to provide anincentive to the seller for the timely delivery of the computers.Paul, along with the buyer on the project team, has agreed that theselected seller will be paid the cost of the computers plus a 10%fee. Which contract type is being used in this case? "

A. Cost plus a percentage of cost contract

B. T&M with incentive

C. Cost plus a fixed fee

D. Fixed Cost.