12. During whatprocess of Project Procurement Management does the buyer of inspectand verify whether or not the products, services, or deliverablesprovided by the seller meet the buyer’s acceptance criteria?
  A. Close Procurements
  B. Change Control.
  C. Acceptance Plan and Verification Process.
  D. Conduct Procurements