Norwegian Satellite Development Company (NSDC)

Cost Estimates for World Satellite Telephone Exchange Project

NSDC has a contract to produce eight satellites to support a worldwide

telephone system (for Alaska Telecom, Inc.) that allows individuals to use a

single, portable telephone in any location on earth to call in and out. NSDC will

 develop and produce the eight units. NSDC has estimated that the R&D

costs will be NOK (Norwegian Krone) 12,000,000. Material costs are expected

 to be NOK 6,000,000. They have estimated that the design and production

 of the first satellite will require 100,000 labor hours, and an 80 percent

 improvement curve is expected. Skilled labor cost is NOK 300 per hour.

 Desired profit for all projects is 25 percent of total costs.

1.      How many labor hours should the eighth satellite require?

2.      How many labor hours for the whole project of eight satellites?

3.      What price would you ask for the project? Why?

4.      Midway through the project your design and production people realize that a

5.      75 percent improvement curve is more appropriate. What impact does this

6.      have on the project?

7.      Near the end of the project, Deutsch Telefon AG requests a cost estimate for

8.       four satellites identical to those you have already produced. What price will

9.      you quote them? Justify your price.