Consider a production
line with five stations. Station 1 can produce a unit in 9 minutes. Station 2
can produce a unit in 10 minutes. Station 3 has two identical machines, each of
which can process a unit in 12 minutes (each unit only needs to be processed on
one of the two machines. Station 4 can produce a unit in 5 minutes. Station 5
can produce a unit in 8 minutes. Which station is the bottleneck station?
o
Station 1
o
Station 2
o
Station 3
o
Station 4
o
Station 5
Question 2
Which of the following
products is likely to be assembled on a repetitive process line?
o
automobiles
o
custom personal computers
o
custom cakes
o
steel
o
beer
Question 3
High fixed costs and
low variable costs are typical of which approach?
o
product
o
process
o
mass customization
o
repetitive
o
A and C
Question 4
The staff training
center at a large regional hospital provides training sessions in CPR to all
employees. Assume that the capacity of this training system was designed to be
1200 employees per year. Since the training center was first put into use, the program
has become more complex, so that 1050 now represents the most employees that
can be trained per year. In the past year, 950 employees were trained. The
efficiency of this system is approximately ________ and its utilization is
approximately ________.
o
79.2 percent; 90.5 percent
o
90.5 percent; 79.2 percent
o
87.5 percent; 950 employees
o
950 employees; 1050 employees
o
110.5 percent; 114.3 percent
Question 5
Effective capacity ×
Efficiency equals:
o
efficient capacity.
o
utilization.
o
actual capacity.
o
expected output.
o
design capacity.
Question 6
One fundamental
difference between a process chart and a flowchart is that:
o
the process chart adds a time dimension
to the horizontal axis, while a flowchart is not time-oriented.
o
the process chart includes the supply
chain, while the flowchart stays within an organization.
o
the process chart is more like a table,
while the flowchart is more like a schematic diagram.
o
the process chart focuses on the
customer and on the provider's interaction with the customer, while the
flowchart does not deal directly with the customer.
o
None of these is true, because a process
chart and a flowchart are the same thing.
Question 7
The Academic Computing
Center has five trainers available in its computer labs to provide training
sessions to students. Assume that the design capacity of the system is 1900
students per semester and that effective capacity equals 90% of design
capacity. If the number of students who actually got their orientation session
is 1500, what is the efficiency of the system?
o
1350 students
o
1710 students
o
78.9%
o
87.7%
o
90%
Question 8
Which of the following
is FALSE regarding repetitive processes?
o
They use modules.
o
They allow easy switching from one
product to the other.
o
They are the classic assembly lines.
o
They have more structure and less
flexibility than a job shop layout.
o
They include the assembly of basically
all automobiles.
Question 9
Which of the following
is true regarding the concept of flexibility?
o
It is the ability to respond with little
penalty in time, cost, or customer value.
o
It may be accomplished with digitally
controlled equipment.
o
It may involve modular or movable
equipment.
o
All of the above are true.
o
None of the above is true.
Question 10
Consider the assembly line below. The three fabrication operations run in parallel, such that each batch of 20 units only needs to go through one of the three fabrication operations. After that, each batch needs to go through both assembly operations, which occur simultaneously (specifically, 10 components are made for each unit in the fabrication stage—some components are then assembled in the Assembly 1 area while others are assembled in the Assembly 2 area). The units are packaged and made ready for shipment in the final stage.
What is the bottleneck
time per batch of this operation?
o
24 min.
o
8 min.
o
88 min.
o
34 min.
o
3 min.
Question 11
Which of the following
technologies could enable a cashier to scan the entire contents of a shopping
cart in seconds?
o
ASRS
o
AGV
o
CAD/CAM
o
RFID
o
FMS
Question 12
A work system has five
stations that have process times of 5, 9, 4, 9, and 8. What is the throughput
time of the system?
o
4
o
9
o
18
o
35
o
7
Question 13
In "drum, buffer,
rope," what provides the schedule, i.e. the pace of production?
o
drum
o
buffer
o
rope
o
all three of the above in combination
o
none of the above
Question 14
Utilization will always
be lower than efficiency because:
o
effective capacity is less than design
capacity.
o
effective capacity is greater than
design capacity.
o
effective capacity equals design
capacity.
o
expected output is less than actual
output.
o
expected output is less than rated
capacity.
Question 15
Process X has fixed
costs of $10,000 and variable costs of $2.40 per unit. Process Y has fixed costs
of $9,000 and variable costs of $2.25 per unit. Which of the following
statements is TRUE?
o
The crossover point is approximately
6667 units.
o
It is impossible for one process to have
both of its costs lower than those of another process.
o
Process Y is cheaper than process X at
all volumes.
o
Process X should be selected for very
large production volumes.
o
Process X is more profitable than
process Y and should be selected.
Question 16
Process A has fixed
costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of
$500 and variable costs of $15 per unit. What is the crossover point between
process A and process B?
o
50 units
o
200 units
o
$2,500
o
$5,000
o
$9,500
Question 17
Which of the following
are all strategies for improving productivity in services?
o
separation, self-service, automation,
and scheduling
o
lean production, strategy-driven
investments, automation, and process focus
o
reduce inventory, reduce waste, reduce
inspection, and reduce rework
o
high interaction, mass customization,
service factory, and just-in-time
o
process focus, repetitive focus, product
focus, and mass customization focus
Question 18
The Theory of
Constraints (TOC) strives to reduce the effect of constraints by:
o
offloading work from constrained
workstations.
o
increasing constrained workstation
capability.
o
changing workstation order to reduce
throughput time.
o
A and B
o
A, B, and C
Question 19
A job shop is an
example of a(n):
o
repetitive process.
o
continuous process.
o
line process.
o
intermittent process.
o
specialized process.
Question 20
Which of the following
phrases best describes process focus?
o
low volume, high variety
o
Finished goods are usually made to a
forecast and stored.
o
Operators are less broadly skilled.
o
high fixed costs, low variable costs