Vikas

CIS/554 CIS554 CIS 554 Week 5 Discussion 2 Estimation Techniques

CIS 554 Week 5 Discussion 2

"Estimation Techniques" Please respond to the following:

•	There are various methods that may be used to determine activity estimates with respect to resources, costs, and durations. Choose at least three estimation techniques that may be used for determining activity estimates for an IT project. Describe the pros and cons of each. Determine the most efficient estimation technique for an IT project; include an example or scenario to support your response.
•	Describe the accuracy level and the risk level of effort and the activities associated with each estimation technique you chose in Part 1 of this discussion. Determine the technique that would be efficient for the following:
1.	 Estimating a source code based project 
2.	 Systems development project
 High-risk software project
Answered
Other / Other
30 Jul 2016

Answers (1)

  1. Vikas

    CIS/554 CIS554 CIS 554 Week 5 Discussion 2 Estimation Techniques

    Estimation is all about estimating the project constraints, which include Scope, Quality, Schedule, ****** ******
    To see full answer buy this answer.
    Answer Attachments

    1 attachments —

    • img
      Week_5_Discussion_2_Ans396516.docx

Report As Dispute

Share Your Feedback

Give Review : A+ A B C D F