Vikas

BUS/517 BUS517 BUS 517 Week 3 Discussion

BUS 517 Week 3 Discussion

Week 3 Discussion
•	5
"Project Scope and Work Breakdown Structure (WBS)" Please respond to the following:
•	Select a project, and determine at least two (2) aspects of the project scope that might have the tendency to go out of scope and potentially derail the project. Next, develop a WBS that contains the three (3) levels of detail and takes the two (2) eventualities you determined into account.

Answered
Other / Other
30 Jul 2016

Answers (1)

  1. Vikas

    BUS/517 BUS517 BUS 517 Week 3 Discussion

    An example of a project that could have a tendency to go out of scope is the relocation of an existi ****** ******
    To see full answer buy this answer.
    Answer Attachments

    1 attachments —

    • img
      Week_3_Discussion_Ans396186.docx

Report As Dispute

Share Your Feedback

Give Review : A+ A B C D F