What is the total labor cost variance for Job 1.Jacques Company planned to use 18,000 pounds of material costing $2.50 per pound to make 4,000 units of its product. In actually making 4,000 units, the company used 18,800 pounds that cost $2.54 per pound. Calculate the direct materials quantity variance. 2.Job #305 was budgeted to require 3.5 hours of labor at $11.00 per hour. However, it was completed in 3 hours by a person who worked for $14.00 per hour. What is the total labor cost variance for Job #305? Business Management Assignment Help, Business Management Homework help, Business Management Study Help, Business Management Course Help