XT.” Students will read and respond to the following:
- Using the “complexity weighting” scheme
shown in Table 5.2 and the function
Point complexity weighted table
shown below, estimate the total function point

Count. Assume historical data
suggest five function points equal one person a

Month and six people can work on
the project.


Complexity
Weight Table

Number of inputs 10 Rated
complexity low

Number of outputs 20 Rated complexity average

Number of inquiries 10 Rated complexity average

Number of files 30 Rated complexity high

Number of interfaces 50 Rated complexity high

- Answer the following questions:

1- What is the estimated project duration?

2- If 20 people are available for the
project, what is the estimated project?

Duration?

 If the project must be completed in six
months, how many people will

be needed for the project?

- Discuss your thought process as you
completed this exercise. How did you

Solve it?


Business Assignment Help, Business Homework help, Business Study Help, Business Course Help
Answered
Other / Other
31 Dec 2015

Answers (1)

  1. Vikas

    Firewall Project

    For this particular project there is a need of 30 to 40 people team which w ****** ******
    To see full answer buy this answer.
    Answer Attachments

    1 attachments —

    • img
      BUS_517_Firewall_Project_XT187146.docx

Report As Dispute

Share Your Feedback

Give Review : A+ A B C D F