Vikas

Project Management

You are the general manager of a large construction project. The contract has both financial incentives for finishing on time or early as well as large penalties if the project is completed late. You know that to get it done on time or early, project planning using a formal time line is essential.
Address the following questions:
In terms of creating a timeline, what is meant by the critical path of a PERT chart?
As a project manager you know that the fastest possible time a project can be completed is known as the critical path. This implies that any delay in any step of a projects critical path, will therefore delay the overall project. On a particular project, step B is part of the critical path; step C and D both are not. Assume that all of these steps, B, C, and D are at risk of being delayed due to some issue (could be lack of people, lack of materials, equipment downtime—it makes no difference). 
How would the manager go about prioritizing correction of the problem existing in B, C, or D? 
Should the manager address the issue in step B first, step C first, or step D first; why? 
Once repair is completed in step #2, how would go you about prioritizing repairs at the other two steps? 

Answered
Other / Other
28 Dec 2015

Answers (1)

  1. Vikas

    Project Management

    The manager has identified that due to lack of people an ****** ******
    To see full answer buy this answer.
    Answer Attachments

    1 attachments —

    • img
      Project_Management182056.doc

Report As Dispute

Share Your Feedback

Give Review : A+ A B C D F