Vikas

MAT540/MAT 540 WEEK 7 QUIZ VERSION 1

MAT 540
WEEK 7
  
A feasible solution violates at least one of the constraints. 
 
Answer



 
In minimization LP problems the feasible region is always below the resource constraints. 
 
Answer



 
Graphical solutions to linear programming problems have an infinite number of possible objective function lines. 
 
Answer



 
The following inequality represents a resource constraint for a maximization problem: 
                                                                X + Y ≥ 20 
 
Answer



 
A linear programming problem may have more than one set of solutions.
 
Answer



 
Surplus variables are only associated with minimization problems. 
 
Answer



 
In a linear programming problem, all model parameters are assumed to be known with certainty. 
 
 
Answer



 
The following is a graph of a linear programming problem. The feasible solution space is shaded, and the optimal solution is at the point labeled Z*. 
 
 
 
 
 
Which of the following constraints has a surplus greater than 0?
Answer



 
The production manager for the Coory soft drink company is considering the production of 2 kinds of soft drinks: regular and diet. Two of her limited resources are production time (8 hours = 480 minutes per day) and syrup (1 of her ingredients) limited to 675 gallons per day. To produce a regular case requires 2 minutes and 5 gallons of syrup, while a diet case needs 4 minutes and 3 gallons of syrup. Profits for regular soft drink are $3.00 per case and profits for diet soft drink are $2.00 per case. For the production combination of 135 cases of regular and 0 cases of diet soft drink, which resources will not be completely used?
Answer



 
The following is a graph of a linear programming problem. The feasible solution space is shaded, and the optimal solution is at the point labeled Z*. 
 
 
 
Which of the following points are not feasible?
Answer



 
The production manager for the Coory soft drink company is considering the production of 2 kinds of soft drinks: regular (R) and diet(D). Two of the limited resources are production time (8 hours = 480 minutes per day) and syrup limited to 675 gallons per day. To produce a regular case requires 2 minutes and 5 gallons of syrup, while a diet case needs 4 minutes and 3 gallons of syrup. Profits for regular soft drink are $3.00 per case and profits for diet soft drink are $2.00 per case. What is the time constraint?
Answer



 
In a linear programming problem, the binding constraints for the optimal solution are: 
            5x1 + 3x2 ≤ 30 
            2x1 + 5x2 ≤ 20 
Which of these objective functions will lead to the same optimal solution?
Answer



 
The following is a graph of a linear programming problem. The feasible solution space is shaded, and the optimal solution is at the point labeled Z*. 
 
 
 
 
The equation for constraint DH is:
Answer



 
Decision variables
Answer



 
In a linear programming problem, a valid objective function can be represented as
Answer



 
Cully furniture buys 2 products for resale: big shelves (B) and medium shelves (M). Each big shelf costs $500 and requires 100 cubic feet of storage space, and each medium shelf costs $300 and requires 90 cubic feet of storage space. The company has $75000 to invest in shelves this week, and the warehouse has 18000 cubic feet available for storage. Profit for each big shelf is $300 and for each medium shelf is $150. What is the maximum profit?
Answer



 
The linear programming problem:
 
MIN Z =          2x1 + 3x2 
Subject to:       x1 + 2x2 ≤ 20 
                        5x1 + x2 ≤ 40 
                        4x1 +6x2 ≤ 60 
                        x1 , x2 ≥ 0 ,
Answer



 
A graphical representation of a linear program is shown below. The shaded area represents the feasible region, and the dashed line in the middle is the slope of the objective function. 
 
 
 
What would be the new slope of the objective function if multiple optimal solutions occurred along line segment AB? Write your answer in decimal notation.
 
Answer



 
Consider the following minimization problem: 
Min z =     x1 + 2x2 
s.t.             x1 + x2 ≥ 300 
                  2x1 + x2 ≥ 400 
                  2x1 + 5x2 ≤ 750 
                  x1, x2 ≥ 0 
 
Find the optimal solution. What is the value of the objective function at the optimal solution? Note: The answer will be an integer. Please give your answer as an integer without any decimal point. For example, 25.0 (twenty five) would be written 25
Answer



 
Max Z =    $3x + $9y 
Subject to:       20x + 32y ≤ 1600 
                        4x + 2y ≤ 240 
                        y ≤ 40 
                        x, y ≥ 0 
At the optimal solution, what is the amount of slack associated with the second constraint?
Answer



Answered
Other / Other
16 Dec 2015

Answers (1)

  1. Vikas

    MAT540/MAT 540 WEEK 7 QUIZ VERSION 1

    Max Z = $3x + $9y Subject to: 20x + 32y ≤ 1600 ****** ******
    To see full answer buy this answer.
    Answer Attachments

    1 attachments —

    • img
      quiz_3_Version_1_New170856.doc

Report As Dispute

Share Your Feedback

Give Review : A+ A B C D F