1. Question : A formal financial review process is always necessary, even when a PM uses project cost control because of the many uncertainties with cost control.
Question 2. Question : The 50/50 rule is used for packages with a very long duration.
Question 3. Question : In the time - cost analysis, the relationship between time and money generally has what shape on a graph?
Question 4. Question : The following is the cost of all progress achieved on the project, or part of the project, and represents what has been spent.
Question 5. Question : The Estimated Cost at completion is the sum of the costs incurred to date and the revised estimated costs for the work remaining. It is computed by the formula BAC/CPI.
Question 6. Question : Which of the following is the first step in measuring and monitoring progress and performance?
Question 7. Question : A project variance can only be a positive number.
Question 8. Question : Earned value describes what has been earned, not simply what has been spent.
Question 9. Question : A project variance can either be a positive or a negative number.
Question 10. Question : AC is the sum of the costs incurred to date and the revised estimated costs for the work remaining.