Doug Casey is in charge of planning and coordinating next spring- sales management training program for his company. Doug listed the following activity information for this project.

Activity Immediate Predecessor Optimistic Most probable Pesimistic
A Plan topic - 1.5 2.0 2.5
B Obtain speakers A 2.0 2.5 6.0
C List meeting location - 1.0 2.0 3.0
D Select location C 1.5 2.0 2.5
E Finalize speaker travel plan B,D 0.5 1.0 1.5
F Make final check with speakers E 1.0 2.0 3.0
G Prepare and mail brochure B,D 3.0 3.5 7.0
H Take reservations G 3.0 4.0 5.0
I Handle last minute details F,H 1.5 2.0 2.5


a. Draw a project network
b. Prepare an activity schedule.
c. What is the critical activities and what is the expected project completion time?
d.If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project?