Calculating BCWP Critical Thinking Assignment You are the sponsor for project XY. The project manager has provided you the following three status reports. The project started on 2/1 and it is now the end of the fourth week. Percent -Completion Report Activity Date Started Percent completed Time to Complete (weeks) AB 2/1 100 Completed AC 2/1 60 2 AD 2/1 100 Completed DE Not started - delayed n/a 3 BF 2/14 40 3 Project Planning Budget: Dollars Budgeted Per Week for Each Activity, Project Starting 2/1 Activity Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Total $ AB 2000 2000 2000 6,000 AC 3000 4000 4000 4000 5000 20,000 AD 2000 3000 2500 7,500 BF 2000 3000 4000 3000 3000 15,000 CE 2500 2,500 DE 3500 3500 3500 10,500 EF 3000 3,000 Total: 7000 9000 8500 9500 11,500 10,000 6000 3000 64,500 Cost Summary Week Ending Cumulative to Date Activity Budget Cost Actual (Over) / Under Budget Cost Actual (Over) / Under AB -- -- -- 6000 6200 (200) AC 4000 4500 (500) 15,000 12,500 2500 AD -- 2400 (2400) 7500 7400 100 BF 2000 2800 (800) 2000 4500 (2500) DE 3500 -- 3500 3500 -- 3500 Total 9,500 9,700 (200) 34,000 30,600 3,400 It is now the end of Week 4 and you want to determine the status of the project using earned value management. Complete the table and earned value metrics below. Some of the information has already been entered for you. Activity % Complete Budgeted Cost for Work Scheduled Budgeted Cost for Work Performed Actual cost for Work Performed Cost Variance Schedule Variance Total Budget AB 6200 6000 AC 60 12000 20000 AD 7500 BF 6000 15000 CE 0 0 2500 DE* 0 0 10500 EF 0 0 3000 TOTAL 64500 * Note that activity DE has been delayed and does not impact the calculations Calculate Each of the Following: Cost Variance ($) = BCWP - ACWP Schedule Variance ($) = BCWP - BCWS Schedule Variance (weeks) = Schedule Variance ($) / Average Weekly BCWS Cost-at-completion = rate of spending x Total budget = ACWP / BCWP * Total Budget CPI = BCWP / ACWP SPI = BCWP / BCWS Add your written analysis below by answering three questions: 1. What is the state of the project? 2. Which activity has had the most positive impact on the project? 3. Which activity has had the most negative impact on the project?