Risk Information Sheet

 

Assignment Preparation: Activities include completing the SkillSoft® courses, the Microsoft® PowerPoint® review, independent student reading, and research.

 

  • Complete the Skillsoft® course, "Identifying project risks."
  • Complete the Skillsoft® course, "Performing risk analysis."
  • Complete the Skillsoft® course, "Risk management planning."
  • Complete the Skillsoft® course, "Risk response and control."

 

Assignment: The Stevens Company is converting from the SQL Server database to the Oracle® database. 

 

Using the sample shown below, create a Risk Information Sheet for at least five risks that might be encountered during the conversion.

 

Risk Information Sheet

Risk id: PO2-4-32

Date: 

Probability: 80%

Impact: High

Description:

Over 70% of the software components scheduled for reuse will be integrated into the application. The remaining functionality will have to be custom developed.

Refinement/Context:

  • Certain reusable components were developed by a third party with no knowledge of internal design standards.
  • Certain reusable components have been implemented in a language that is not supported on the target environment.

 

Mitigation/Monitoring:

  • Contact third party to determine conformance to design standards.
  • Check to see if language support can be acquired.

 

Management/Contingency Plan/Trigger:

  • Develop a revised schedule assuming that 18 additional components will have to be built.
  • Trigger: Mitigation steps unproductive as of March 30, 2014

 

Current Status:

In process

Originator:

Jane Manager

 