INF 337 Week 3 Quiz | Assignment Help | Ashford University

INF 337 Week 3 Quiz | Assignment Help | Ashford University 



Question 1

A project variance can either be a positive or a negative number.

 

o   True

o   False

 

Question 2

AC is the actual cost of the work performed.

 

o   True

o   False

 

Question 3

Which of the following is the first step in measuring and monitoring progress and performance?

 

o   All of the above

o   Identify quantitative elements.

o   dentify qualitative elements.

o   Determine what should be measured.

o   Establish a control system that measures the ongoing status of various project activities in real time.

 

 

 

 

 

 

 

Question 4

Which of the following are necessary to correctly and accurately measure and evaluate project performance?

 

o   All of the above

o   taking corrective action

o   comparing actual performance against plan

o   Measuring progress and performance

o   Setting a baseline plan

 

Question 5

Any significant deviations between actual and planned budget expenditures constitute what?

 

o   All of the above.

o   None of the above

o   A project that has been cancelled.

o   A project on budget and on schedule

o   A potential problem that must be investigated.

 

 

Question 6

The 50/50 rule is used for packages with a very long duration.

 

o   True

o   False

 

 

 

 

Question 7

AC is the sum of the costs incurred to date and the revised estimated costs for the work remaining.

 

o   True

o   False

 

Question 8

A formal financial review process at the managerial level is not necessary when a PM uses project cost control.

 

o   True

o   False

 

Question 9

The following is the cost of all progress achieved on the project, or part of the project, and represents what has been spent.

 

o   All of the above.

o   ETC

o   CV

o   AC

o   EV

 

 

Question 10

 The 0/100 rule can have an activity that is 100% complete or 0% complete.

 

o   True

o   False

Answer Detail

Get This Answer

Invite Tutor