1.                                                    

A

-

6

B

A

3

C

A

7

D

C

2

E

B,D

4

F

D

3

G

E,F

7

 

 

The following activities are part of a project to be scheduled using CPM: Activity       Immediate Predecessor           Time (wks)

 

 

 

 

 

 

a.  Draw the network

b.  What is the critical path?

c.  How many weeks will it take to complete the project?

d.  How much slack does activity B have?

 