Business Management Assignment Help
- Emirates College Of Technology / BUS 407
- 20 Mar 2021
- Price: $20
- Management Assignment Help / Operation Management Assignment Help
Business Management Assignment Help
Case Study: Risk Management and Evaluation
Nuclear energy is one of the possible
alternative energy to meet the increasing energy demand in the world. Unlike
coal and gas, nuclear power can be considered as clean from pollution. In this
context, the UAE has increased its focus on this energy in order to comply with
its vision of being a clean industrial country that sustain environment and
people. As the risk manager of a project sponsored by Barakah, you are assigned
the role of managing and evaluating risks that might affect the project during
the execution phase. The project is scheduled to start from July 2021, it consists
of power plant extension that include expanding the power plant building and
installing new electrical machines to boost the produced electric power. During
a brain storming session, you discovered that the current pandemic, due the
COVID-19, could be a triggering event that might lead to the occurrence of
several risky events. The following represents data about the project prior to
the risk study:
Activity |
Description |
Immediate Predecessor |
Activity Time : T (in days) |
A |
Plant specifications study |
— |
5 |
B |
environmental impact study |
A |
6 |
C |
Engineering study |
A |
8 |
D |
Demolition, remodeling, and dust control |
B |
12 |
E |
Enter additional electrical machines and equipment |
B |
20 |
F |
Job-site security |
B,C |
16 |
G |
On site execution of the building extension |
D,E |
25 |
H |
On site execution of the machinery implementation |
F |
35 |
I |
Testing the new building with machines onboard |
F |
20 |
J |
security control and safety monitoring |
G,H,I |
14 |
Table: Power Plant Extension
Project – Data
Part I:Risk Management
As the head of the project risk management
team, you will perform some of the risk management steps by replying to the
following questions:
Questions:
1. Propose four possiblerisk events that
could be triggered by the COVID-19 pandemic and explain how they might affect
the project.
2. For each proposed risk event,
propose a risk response plan to face or overcome the risk (Note that risk response plans
should be different for each risk event).