Question 1
A pure project
organizational structure houses the project in a specific functional area.
o
True
o
False
Question 2
A master production
schedule is a schedule that specifies the timing, size, and sequence of
production for aggregated product families.
o
True
o
False
Question 3
Which one of the
following statements concerning production and staffing plans is BEST?
o
Production plans are based primarily on
information from the master production plan.
o
A master production schedule is a
projected statement of income, costs, and profits.
o
Aggregation can be performed along three
dimensions: product families, labor, and time.
o
A staffing plan is the intermediate link
between the business plan and the master production schedule.
Question 4
Dependent demand for an
item occurs because the quantity required for it varies with the production
plans of one or more parents.
o
True
o
False
Question 5
Which one of the
following statements about managerial inputs to production and staffing plans
is BEST?
o
Materials provide the current staffing
level.
o
Human resources provide the training
capacity and labor-market conditions. Marketing provides the schedule of sales
associates.
o
Finance provides labor and machine
standards.
Question 6
A(n) project is an
interrelated set of activities that has a definite starting and ending point
and that results in a unique outcome for a specific allocation of resources.
Question 7
The employees of Global
Bike Incorporated specialized in either their mountain bike or touring bike
line, but there were a few workers that were equally adept at assembling either
product. For sales and operations planning purposes, the latter group could be:
o
Reassigned.
o
Aggregated.
o
Subcontracted.
o
Over timed.
Question 8
Heidi was part of a
project team that retained their roles within the organization and was on loan
to the project due to her technical expertise. In effect, she reported to two
bosses, one in her functional area and also to the project manager. Heidi is
operating within a(n) matrix organizational structure.
Question 9
In MRP, a(n) parent is
any item manufactured from one or more components.
Question 10
Gross requirements are
the total demand derived from all parent production plans.
o
True
o
False
Question 11
The projected on-hand
inventory in the MPS takes into account scheduled receipts, but not planned
receipts.
o
True
o
False
Question 12
The projected on-hand
inventory in the MPS takes into account customer orders (booked) as well as the
MPS quantities.
o
True
o
False
Question 13
Under which one of the
following circumstances can an MRP system be used to its best advantage?
o
When the item's demand depends on the
production plans of its parent(s)
o
When the item's demand depends only on
customer demand
o
When the item's demand is constant
o
When the item's demand is uniform
Question 14
A product family is a
group of customers, services, or products that have similar demand requirements
and common processes, labor, and materials requirements.
o
True
o
False
Question 15
Scope creep is one of
the primary causes of project failure.
o
True
o
False