BUSI 313 Week 4 Quiz | Project Management Assignment Help | Liberty University
- Liberty University / BUSI 313
- 08 Feb 2019
- Price: $13
- Other / Other
- BUSI 313 Week 4 Quiz | Project Management Assignment Help | Liberty University
- Question 1
Which of
the following is NOT one of the items that would appear on a project scope
statement or checklist? |
- Question 2
The
project charter provides the project manager with written authority to use
organizational resources for project activities. |
- Question 3
For
large companies, the organization breakdown structure is used rather than the
work breakdown structure. |
- Question 4
Project
scope describes what you expect to deliver to your customers when the project
is complete. |
- Question 5
A
“Dissemination Mode” is |
- Question 6
Process
breakdown structures are used when the size and the scope of the project do
not warrant an elaborate WBS or OBS. |
- Question 7
The
highest element in the hierarchical breakdown of the WBS is |
- Question 8
One of
the items included on a project scope statement or checklist is the review
with the customer. |
- Question 9
Which of
the following is least likely to be included in a work package? |
- Question 10
Estimating
the total cost of a house by multiplying the total square feet by cost per
square foot is an example of the apportion method of estimating costs. |
- Question 11
Accounting
would be an example of which of the following costs typically found in a
project? |
- Question 12
Large
projects that have long time horizons and a very high complexity can be
referred to as |
- Question 13
Cost,
time, and budget estimates are the lifeline for control; they serve as the
standard for comparison of the actual and the planned throughout the life of
the project. |
- Question 14
Rob is
responsible for estimating a work package that has a significant amount of
uncertainty associated with the time and cost to complete. Due to the
uncertainty involved he will be making a low, an average and a high estimate.
Rob is using which estimating approach? |
- Question 15
Estimating
can be challenged by |
- Question 16
A good
starting point for developing time and cost estimates is |
- Question 17
Top-down
estimates usually are derived from someone who uses experience and/or
information to determine the project duration and total cost. |
- Question 18
________
activities are to be completed immediately following a particular activity. |
- Question 19
Activities
which can take place at the same time are termed |
- Question 20
Burst
activities have more than one activity immediately following them (more than
one dependency arrow flowing from them). |
- Question 21
System
documentation cannot end until three days after testing has started. This is
an example of which kind of lag? |
- Question 22
________
activities must be completed immediately before a particular activity. |
- Question 23
The
critical path in a project network is the |
- Question 24
Even
though a project costs time and money to develop, it is worth the effort. |
- Question 25
It is
possible for a project network to have more than one critical path. |