  • Question 1

Which of the following is NOT one of the items that would appear on a project scope statement or checklist?

 

  • Question 2

The project charter provides the project manager with written authority to use organizational resources for project activities.

  • Question 3

For large companies, the organization breakdown structure is used rather than the work breakdown structure.

  • Question 4

Project scope describes what you expect to deliver to your customers when the project is complete.

  • Question 5

A “Dissemination Mode” is

  • Question 6

Process breakdown structures are used when the size and the scope of the project do not warrant an elaborate WBS or OBS.

  • Question 7

The highest element in the hierarchical breakdown of the WBS is

 

  • Question 8

One of the items included on a project scope statement or checklist is the review with the customer.

 

  • Question 9

Which of the following is least likely to be included in a work package?

 

  • Question 10

Estimating the total cost of a house by multiplying the total square feet by cost per square foot is an example of the apportion method of estimating costs.

 

  • Question 11

Accounting would be an example of which of the following costs typically found in a project?

  • Question 12

Large projects that have long time horizons and a very high complexity can be referred to as

 

  • Question 13

Cost, time, and budget estimates are the lifeline for control; they serve as the standard for comparison of the actual and the planned throughout the life of the project.

 

  • Question 14

Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach?

 

  • Question 15

Estimating can be challenged by

 

  • Question 16

A good starting point for developing time and cost estimates is

 

  • Question 17

Top-down estimates usually are derived from someone who uses experience and/or information to determine the project duration and total cost.

  • Question 18

________ activities are to be completed immediately following a particular activity.

 

  • Question 19

Activities which can take place at the same time are termed

  • Question 20

Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).

 

  • Question 21

System documentation cannot end until three days after testing has started. This is an example of which kind of lag?

  • Question 22

________ activities must be completed immediately before a particular activity.

  • Question 23

The critical path in a project network is the

 

  • Question 24

Even though a project costs time and money to develop, it is worth the effort.

  • Question 25

It is possible for a project network to have more than one critical path.

 