- Question
1
If a
project criterion should be optimized if at all possible, it is classified as
being constrained. |
- Question
2
Responsibility
matrices are used primarily with small and medium-sized projects and have
limited use in large projects. |
- Question
3
All of
the following are ways the WBS helps in managing projects EXCEPT |
- Question
4
During
the course of a project, it is possible that the project priorities may
change. |
- Question
5
One of
the primary jobs of a project manager is to manage the trade-offs associated
with the project. Which of the following is NOT one of the basic
classifications of project priorities? |
- Question
6
An
expected output over the life of a project would be classified as a target. |
- Question
7
Linda
has just been assigned manager of a project to develop a new advertising campaign
for an established product. Her first step should be to |
- Question
8
Jose is
looking at a document that outlines the specific deliverables and
sub-deliverables required to complete the writing of a technical support
manual. He is most likely viewing the |
- Question
9
The
intersection of work packages and the organizational unit creates a project control
point called a cost account. |
- Question
10
Which
of the following is a good condition for bottom-up estimating? |
- Question
11
Which
of the following methods is NOT considered a top-down approach to estimating
project time and cost? |
- Question
12
Richard
is collecting estimates for a house that he will have the funding to build in
12 months. Which of the following factors does Richard need to consider in
regard to the quality of these estimates? |
- Question
13
An
external view of a Mega Project based upon the outcome of similar projects
undertaken in the past is known as: |
- Question
14
Reasons
why estimating time and cost are important include all of the following
EXCEPT |
- Question
15
If time
and costs are important to a project the top-down approach to estimating time
and costs for the project is the best choice. |
- Question
16
Estimates
that are typically based on estimates of elements found in the work breakdown
structure are called bottom-up estimates. |
- Question
17
Refining
Estimates may be necessary for a number of reasons. For example, a manager
getting further into a project and obtaining a better understanding of what
needs to be done to accomplish a project and meet the needs of the customer
is an example of |
- Question
18
The
assumption that all immediate preceding activities must be 100% complete is
too restrictive in some situations. When an activity is broken down into
smaller segments in order to start the succeeding activity sooner, this is
called |
- Question
19
Using
free slack does not delay any following activities and requires no coordination
with managers of other activities. |
- Question
20
The
backward pass determines project duration. |
- Question
21
The
minimum amount of time a dependent activity must be delayed to begin or end
is referred to as |
- Question
22
When
translated into a project network, a work package will become |
- Question
23
An
activity that has more than one dependency arrow flowing into it is termed
a(n) |
- Question
24
One
piece of information that the arrows within the Activity-on-Node network can
convey is |
- Question
25
The
amount of delay within a task that will not delay the overall project is
known as a |