Question 1
Question text
Please select which of the following statements are true.
Select one:
Question 2
Question text
Please select which of the following statements is the most accurate.
Select one:
Question 3
Question text
What determines how the team knows when a Sprint Backlog item is done?
Select one:
Question 4
Question text
What does the Scrum Development Team attempt to develop every Sprint?
Select one:
Question 5
Question text
What is the maximum amount of time that the team should spend in the daily scrum?
Select one:
Question 6
Question text
What is the maximum amount of time that the team should spend in the daily standup?
Select one:
Question 7
What is the primary objective of the daily scrum?
Select one:
Question 8
Question text
Which of the following does not occur during Sprint execution?
Select one:
Question 9
Question text
Which of the following is not reflected in a Sprint Burndown Chart?
Select one:
Question 10
Question text
Which of the following is reflected in a Sprint Burndown Chart?
Select one:
Question 11
Question text
Which of the statement below is a key reason to implement Scrum in an organization?
Select one:
Question 12
Question text
Which one of following options list activities in the correct order?
Select one:
Question 13
Question text
Which question below is each team member asked to answer at the daily scrum?
Select one:
Question 14
Question text
Which question below is each team member asked to answer at the daily scrum?
Select one:
Question 15
Question text
Which statement below best describes the primary objective of a Sprint Burndown Chart?
Select one:
Question 16
Question text
Which statement below best describes the primary objective of the Sprint Retrospective?
Select one:
Question 17
Question text
Which statement below best describes the primary objective of the Sprint Review?
Select one:
Question 18
Question text
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
Select one:
Question 19
Question text
You are a new Scrum Master and the Scrum team is about to start their very first sprint. What guidance should you provide on what they should produce in Sprint One?
Select one:
Question 20
Question text
You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite for the Sprint Review to demo the items completed in the Sprint. Who should you invite as a required attendee to the Sprint Review - 1. Product Owner(s), 2. Scrum Team, 3. Other internal stakeholders?
Select one:
Question 21
Question text
You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite for the Sprint Review to demo the items completed in the Sprint. Who should you invite as an optional attendee to the Sprint Review - 1. Product Owner(s), 2. Scrum Team, 3. Business Users?
Select one:
Question 22
Question text
You are the Scrum Master for five Scrum teams which have a combined total of three Product Owners. The Scrum teams are assigned to work on different components of the same product. How should you set up the Sprint cycle to execute Scrum?
Select one:
Question 23
Question text
You are the Scrum Master for five Scrum teams which have a combined total of three Product Owner. The Scrum teams are assigned to work on different components of the same product. When should all of Sprint deliverables be integrated?
Select one:
Question 24
Question text
You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the team handle the remaining three tasks?
Select one: