Unit 10 Final Project Release and Sprint Planning
After a prioritized, estimated product backlog is created then a release plan can be created and finally sprint planning can take place.
Here are the assumptions for this assignment:
The average velocity of your team is 20 story points per sprint
Sprints are 2 weeks in duration
You have a team of 3 developers and 2 testers in your scrum team along with the ScrumMaster and product owner.
1. Split your user stories into as many sprints as necessary to consume all of the story points based on 20 story points velocity (maximum number of story points per sprint) for each sprint
2. Create that number of sprints in your Scrummage project and place each user story into a sprint based on prioritization, the number of story points, and velocity. Remember, although your velocity is 20 you do not need to have exactly 20 story points in each sprint, they can go over or under by 1 or 2 depending on the prioritization. The user story prioritization should be the number of factor to use when determining the sprint a user story goes into.
3. After all user stories are allocated to sprints then begin to build the sprint backlog for sprint 1. For each user story in sprint 1 create a set of tasks that would be required to complete that user story. If you are not familiar with software development you can use these tasks: Design, Develop, and Test.
4. Have each team member pick one or more user stories they would work on and put their name on the tasks for the user stories they would work on.
5. After tasks are associated with a team member that team member will associate hours with each task. Make sure to fill in the estimated hours and remaining hours with the same number. Also fill out 0 as the hours completed. This listing of user stories, tasks, and hours within a sprint is called the sprint backlog.
6. You will also need to begin simulating 2 sprints of 2 weeks each. Review Final Project Unit 14 – Team Project Scrum and Scrummage for instructions on how to simulate two sprints.
Deliverables:
1. Submit a single word document which includes screenshots of your release plan, showing each sprint and the user stories associated with that sprint
2. Submit a single word document which includes screenshots of your sprint 1 sprint backlog. This should include the user stories associated with the sprint and the tasks associated with each user story.