Question 1
Question text
According to Rubin, capacity for a Sprint can be measured in story points or Effort-hours
Select one:
Question 2
Question text
According to Rubin, which one of the following is the three different types of detail levels used in Agile?
Select one:
Question 3
Question text
All but one of the following is a characteristic of story points? Which one is not?
Select one:
Question 4
Question text
All of the following estimation principles are associated with typical plan-driven or waterfall estimation process except one. Which one is associated with the typical agile estimation process. which one of the following is associated with the agile estimation process?
Select one:
Question 5
Question text
All of the following items should be considered in determining the capacity of a sprint but one. Which one should not be considered?
Select one:
Question 6
Question text
If a development team member takes off during a Spring, it is expected that the other team members will pick up the slack for the team member and accomplish the work on the absent person's behalf.
Select one:
Question 7
Question text
In Agile Project Management according to Cobb, more is requested rather than just estimation in a Sprint. The three level of estimates mentioned in Cobb are:
Select one:
Question 8
Question text
In planning poker which one of the following is a the correct sequence
Select one:
Question 9
Question text
Once teams gain experience, story points become very easy and intuitive
Select one:
Question 10
Question text
The Delphi method which planning poker is based on is an unstructured communication technique and non-interactive forecasting method that relies on a panel of experts coming to consensus on an estimate.
Select one:
Question 11
Question text
The portfolio backlog is not a part of Scrum
Select one:
Question 12
Question text
The unit of a story point is a nebulous unit of time. However, some teams use one of the following to be a story point.
Question 13
Question text
When planning and managing the development using Scrum, all of the following questions but one are addressed. Which one is not addressed as it relates to estimation and velocity?
Select one:
Question 14
Question text
Which one of the following is correct relative to planning poker?
Select one:
Question 15
Question text
Which one of the following is not a Product backlog item concept?
Select one:
Question 16
Question text
Which one of the following numbers are not in the Fibonacci sequence used in Planning Poker?
Select one:
Question 17
Question text
Which one of the following statements about estimation is most true?
Select one: