ACC/560 ACC560 ACC 560 WEEK 8 QUIZ

ACC 560 WEEK 8 QUIZ

Week 8 Quiz

  • Question 1
   
 

If the labor quantity variance is unfavorable and the cause is inefficient use of direct labor, the responsibility rests with the

     
   
   
     
  • Question 2
   
 

Using standard costs

     
   
   
     
  • Question 3
   
 

Unfavorable materials price and quantity variances are generally the responsibility of the
Price Quantity

     
   
   
     
  • Question 4
   
 

Budget data are not journalized in cost accounting systems with the exception of

     
   
   
     
  • Question 5
   
 

A managerial accountant
1. does not participate in the standard setting process.
2. provides knowledge of cost behaviors in the standard setting process.
3. provides input of historical costs to the standard setting process.

     
   
   
     
  • Question 6
   
 

Scorpion Production Company planned to use 1 yard of plastic per unit budgeted at $81 a yard. However, the plastic actually cost $80 per yard. The company actually made 3,900 units, although it had planned to make only 3,300 units. Total yards used for production were 3,960. How much is the total materials variance?

     
   
   
     
  • Question 7
   
 

The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1,800 units, the actual direct labor cost was $48,000 for 3,000 direct labor hours worked, the total direct labor variance is

     
   
   
     
  • Question 8
   
 

Clark Company manufactures a product with a standard direct labor cost of two hours at $18.00 per hour. During July, 2,000 units were produced using 4,200 hours at $18.30 per hour. The labor price variance was

     
   
   
     
  • Question 9
   
 

Hofburg’s standard quantities for 1 unit of product include 2 pounds of materials and 1.5 labor hours. The standard rates are $2 per pound and $7 per hour. The standard overhead rate is $8 per direct labor hour. The total standard cost of Hofburg’s product is

     
   
   
     
  • Question 10
   
 

A standard differs from a budget because a standard

     
   
   
     

 

Answer Detail

Get This Answer

Invite Tutor