AC 302 Week 2 Quiz 4 Kiner Inc began work in 2014 on a contract for $16800000 Other data are as follows 2014 2015 Costs incurred to date $7,200,000 $11,200,000 Estimated costs to complete 4,800,000  Billings to date 5,600,000 16,800,000 Collections to date 4,000,000 14,400,000 If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2014 is