AC 302 Week Quiz 3
- University of Phoenix / AC 302
- 02 Sep 2015
- Price: $1
- Other / Other
AC 302 Week Quiz 3 Question Adler Construction Co. uses the percentage of completion method. In 2014, Adler began work on a contract for $6,600,000 and it was completed in 2015. Data on the costs are: Year Ended December 31 2014 2015 Costs incurred $2,340,000 $1,680,000 Estimated costs to complete 1,560,000  For the years 2014 and 2015, Adler should recognize gross profit in 2014 and 2015 of 2014 2015