AC 302 Week 2 Quiz 100% Correct
1 Question In selecting an accounting method for a newly contracted long-term construction project, the principal factor to be considered should be
Question 2. Question : Cost estimates on a long-term contract may indicate that a loss will result on completion of the entire contract. In this case, the entire expected loss should be
Question 3. Question : Adler Construction Co. uses the percentage-of-completion method. In 2014, Adler began work on a contract for $6,600,000 and it was completed in 2015. Data on the costs are:
Year Ended December 31
2014 2015
Costs incurred $2,340,000 $1,680,000
Estimated costs to complete 1,560,000 â€â€
For the years 2014 and 2015, Adler should recognize gross profit in 2014 and 2015 of
2014 2015
Question 4. Question : Kiner, Inc. began work in 2014 on a contract for $16,800,000. Other data are as follows:
2014 2015
Costs incurred to date $7,200,000 $11,200,000
Estimated costs to complete 4,800,000 â€â€
Billings to date 5,600,000 16,800,000
Collections to date 4,000,000 14,400,000
If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2014 is
Question 5. Question : When there is a significant increase in the estimated total contract costs but the increase does not eliminate all profit on the contract, which of the following is correct?