AC 302 Week 2 Quiz 100% Correct
- University of Phoenix / AC 302
- 25 Aug 2015
- Price: $1
- Other / Other
AC 302 Question 4. Question : Kiner, Inc. began work in 2014 on a contract for $16,800,000. Other data are as follows: 2014 2015 Costs incurred to date $7,200,000 $11,200,000 Estimated costs to complete 4,800,000  Billings to date 5,600,000 16,800,000 Collections to date 4,000,000 14,400,000 If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2014 is