What were the weighted-average accumulated expenditures
Use the following information for questions 1 through 4.
On January 2, 2010, Indian River Groves began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2011. Expenditures for the construction were as follows:
January 2, 2010 $200,000
September 1, 2010 600,000
December 31, 2010 600,000
March 31, 2011 600, ...